A successful major kiln shutdown of line ver at KCML
The shudown duration was 10 days to confirm a smooth abd sustained operation going forward. One of the major tasks was to replace the cracked kiln supporting roller of station 2. The job was completed safely, on time and as planned. Thanks to Cementech team’s dedication and hardwork!
Rehabilitation Pan conveyor Bazian Cement Plant
Change complete set of rails Change 50% of chain Change damage Pans Change damaged frams Alignment